Certified Maintenance & Reliability Professional (CMRP) Practice Exam

Disable ads (and more) with a membership for a one time $2.99 payment

Prepare for the Certified Maintenance and Reliability Professional Test with flashcards and multiple-choice questions. Understand the exam structure, practice with explanations and hints, and get ready for certification success!

Each practice test/flash card set has 50 randomly selected questions from a bank of over 500. You'll get a new set of questions each time!

Practice this question and more.


In which phase of an asset's life cycle are the highest costs typically incurred?

  1. Design and Development

  2. Operate and Maintain

  3. Decommissioning

  4. Acquisition

The correct answer is: Operate and Maintain

The phase of an asset's life cycle where the highest costs are typically incurred is during the operation and maintenance phase. This phase involves not only the costs associated with the day-to-day functioning of the asset, such as labor, utilities, and materials, but also costs related to preventive and corrective maintenance efforts. During this period, organizations must ensure that the asset operates efficiently, which may require significant investment in manpower and materials as well as system upgrades or repairs. Additionally, over time, the accumulated costs for maintenance activities tend to exceed those incurred during design, acquisition, or decommissioning phases. Furthermore, while design and development, acquisition, and decommissioning phases involve significant expenditures, they are usually one-time costs or incurred over a shorter timeframe compared to the ongoing expenses seen during the operation and maintenance phase. The long-term upkeep and the need for reliability contribute significantly to the financial burden in this phase, making it the most costly part of the asset's life cycle.