Certified Maintenance & Reliability Professional (CMRP) Practice Exam

Disable ads (and more) with a membership for a one time $2.99 payment

Prepare for the Certified Maintenance and Reliability Professional Test with flashcards and multiple-choice questions. Understand the exam structure, practice with explanations and hints, and get ready for certification success!

Each practice test/flash card set has 50 randomly selected questions from a bank of over 500. You'll get a new set of questions each time!

Practice this question and more.


At what stage do most maintenance costs become fixed?

  1. During the operation phase

  2. During the design phase

  3. During the decommissioning phase

  4. During the planning phase

The correct answer is: During the design phase

Most maintenance costs become fixed during the design phase. This is the point at which decisions regarding materials, systems, and components are made, and these choices directly influence the ongoing maintenance requirements and associated costs. For instance, if a robust and reliable design is selected, it may lead to lower maintenance costs in the long run. Conversely, if the design involves complex systems or materials that are prone to failure, this can result in higher maintenance expenditures. Once the design is finalized and the project moves forward, most cost implications related to maintenance are locked in based on those early design decisions. Later phases, such as operation, planning, and decommissioning, can influence operational costs and overall budget but generally do not alter the foundational costs established during the design phase. Thus, understanding the impact of design choices is critical for effective maintenance and reliability planning.